Architectural millwork & joinery tolerances.

Fit is a measured decision.

A joinery drawing should explain how parts meet after conditioning, finishing and assembly. Nominal dimensions alone leave the workshop to invent the most important part: the fit.

Mortise and tenon section study Dimensioned conceptual timber section. Dimensions are illustrative and require project verification. SECTION A—A dimensions in mm GRAIN / DATUM FINISHED STOCK DETAIL
Fig. 4 · Timber section study Schematic / not for fabrication

Specimen schedule

Nominal dimensions are reference examples. Inches, when selected, are rounded to three decimal places.

Feature Reference geometry Nominal size Fit review
Tenon thickness Centred on rail 8 mm Trial against actual cutter
Tenon length Engagement into stile 28 mm Leave glue relief
Rail thickness Finished stock 24 mm Measure after surfacing
Shoulder width Bearing each side 8 mm Check squareness
Mortise depth Blind cavity 30 mm Avoid hydraulic lock
Edge radius Tool-dependent corner 4 mm Match internal radius

Mortise and tenon as a system

Size the joint from the member geometry, load path and machining method. The illustrative section is not a structural approval. A trial joint in the intended material reveals compression, tear-out and assembly force better than an isolated numerical tolerance.

Tolerance belongs to a process

State a datum face and identify critical dimensions. Tool runout, cutter wear and moisture changes can all alter the final fit. Apply the tolerance to the finished condition, and record whether a coating is included in the allowance.

CAD profiles and cutter geometry

Internal corners follow the cutter radius unless a secondary operation changes them. In a CAD profile, distinguish the desired finished boundary from the tool-centre path. Keep compensation in one place so the radius is not applied twice.

Dry assembly before adhesive

Check shoulder contact, alignment and clamp access before adding adhesive. Provide space for excess glue in blind joints and follow the adhesive supplier’s instructions for open time and pressure. A forced dry fit may swell further during bonding.